ZIWAY ALUTO LANGANO GEOTHERMAL PROJECT

photo_2022 06 28_09 07 08 1
photo_2025 08 07_13 17 38 1
placeholder

Project Information

  • Project Owner: Ethiopian Electric Corporation
  • Contractor: FINOT Engineering and Trading PLC.
    with Toyota Tsusho Corporate
  • Project Location: Ziway, Oromia Rigion, Ethiopia
  • Funded by: World Bank(WB) and JICA
  • Project Scope: In conclusion, the project delivers a
    comprehensive approach to construction—from groundwork to final
    finishes—with an emphasis on safety,
    precision, and long-term performance.

Project Overview

The project scope covers essential civil engineering works required for the construction and functional readiness of the geothermal plant. These works include:

  • Execution of all earthworks for plant foundations and site preparation.

  • Construction of plant substructures and superstructures.

  • Culvert construction and installation of all drainage systems, including UPVC and perforated pipes, manholes, geotextile membrane layers, and aggregate backfilling.

  • Culvert construction and installation of all drainage systems, including UPVC and perforated pipes, manholes, geotextile membrane layers, and aggregate backfilling.

  • Development of plant road access and internal circulation routes. ◦ Finishing works for various structures

  • Construction of brine and reinjection pipeline foundations extending 2.5 km.

  • Plant fencing and boundary works.

  • Landscaping works for environmental and functional enhancement of the plant surroundings.