TANA BELES SUGAR FACTORY PROJECT

20250406_120644 scaled
Picture7
placeholder

Project Information

  • Project Owner: ETHIOPIAN SUGAR CORPORATION
  • Contractor: FINOT Engineering and Trading PLC.
    with Nantong Construction Group
    Co. Ltd. (Chines company Ethiopia
    Branch)
  • Project Scope: The project scope involves civil engineering works for the BELES-1 Sugar Factory, including rigid pavement roads, underground structures like foundations and tunnels, superstructure works such as
    slabs and columns, as well as cable trenches, masonry, and finishing tasks like plastering, painting, and tiling

Project Overview

FINOT Engineering and Trading Plc was engaged by Nantong Construction Group Co. Ltd.
(Ethiopia Branch) as a designated sub-contractor for the execution of major civil construction activities within the BELES-1 Sugar Factory Project. The assignment formed part of the
main contract between the Ethiopian Sugar Corporation and Nantong, and required the
delivery of complex and high-quality civil engineering works essential to the factory’s overall infrastructure.
The project scope included a wide range of structural, underground, and finishing works.
Key tasks completed under this contract comprise:

  • Factory Internal Rigid Pavement Road Works, involving the construction of durable internal road networks capable of supporting heavy industrial traffic.

  • Underground Civil Works, including foundations, tunnels, conveyor belt foundations, pedestals, and weight bridge structures.

  • Superstructure Civil Works, such as slabs, columns, conveyor belt pedestals, corbels, and other technically demanding structural components.

  • Cable Trench Construction, supporting the factory’s electrical and communication infrastructure.

  • Masonry Works required for various building components within the facility.

  • Finishing Works, including plastering, painting, and tiling to ensure functional and aesthetic completion of structures.